ACI provided and installed a 360,000 PPH Deaerator, associated piping, insulation, electrical, controls, structural steel & roofing. We performed work on four 80,000 pph water tube boilers.
Chilled Water Piping Upgrade: New 30-inch Chilled water mains and 20-inch chilled water mains installed beneath Monument Street, serving the Johns Hopkins Hospital Campus. Hydraulic analysis was performed to determine capacity to support future Campus growth.
Deaerator Replacement: New 360,000 pph tray-type deaerator installed in Central Steam Plant RI developed design documents and performed construction administration for each of the projects named above.
Work performed by licensed steamfitters and licensed electricians.